Golden Meadow to Clovelly 115kV Energized Rebuild 

Owner

Entergy Services, LLC

Customer/Client

Entergy Louisiana, LLC

Location

Galliano, Louisiana

Period of Performance

June 2021 - March 2022

Diamond D was awarded this vital restoration project which consisted of the energized replacement of the 6.75 mile transmission line due to the impact of Hurricane Zeta which supplies power to Grande Isle and Port Fourchon, Louisiana’s southernmost port, which services over 90% of the Gulf of Mexico’s deepwater oil production and 16 to 19% of the U.S. oil supply. Our team safely performed the installation and removal of all access matting, stream and pipeline crossings, cattle guards, and gates as well as the installation, maintenance and removal of Stormwater Pollution Prevention Plan (SWPPP) Features. Diamond D also performed the unloading and staging of all caissons, structures and conductor, removal and disposal of all demolished structures and conductor, and restoration of all project access roads and off-site laydown areas. 

The DDI team was faced with a major challenge only 26 days into this 9-month project as Category 4 Hurricane Ida made landfall, with the eye of the storm passing less than 10 miles from the project. Hurricane Ida damaged or destroyed more than 80% of the existing Golden Meadow to Clovelly Transmission line, changing the scope of work from an energized reconductor to a complete demolition and rebuild of the transmission line. Faced with major logistical challenges including the lack of daily life-necessities, our team was able to re-mobilize all temporary facilities, project equipment, and personnel. This change of scope necessitated a complete revision of the project execution plan, schedule, and pricing. DDI was able to commence work in less than 10 days after Hurricane Ida’s landfall and zero delays in the project work. 

Accomplishments

Accomplishments

Zero recordable and/or lost time incidents 

Approximately half of the access matting was required to be installed and removed through an energized substation 

All work on this project was 100% self-performed by Diamond D 

Metrics

23,033 ea.
8” x 4’ x 18’ timber access mats 

629 ea.
8” x 16’ laminated access mats 

295 ea.
12” x 4’ x 30’ timber bridge mats 

9,719 tons
of limestone aggregate 73 ea. double access gates and cattle guards